A front of house remodel is five small jobs done in the right order. Wood and water first. Then the door. Then paint. Then the walkway and the landing. Done out of order, you paint twice and the new door frames a rotten fascia. Done as one scope, the front gets finished once.

The front entrance of a house with a walkway, porch and landscaping, front of house remodel
Five small jobs, one order. Wood, door, paint, walkway. Out of order, you paint twice.

A front of house remodel is an order of work, not a shopping list.

Curb appeal pages show before and after photos. None of them shows the order the work happened in. That order decides whether it looks like that in 3 years. Here is what to ask before you hire anyone, including us.

A brick house under renovation with the front opened up, front of house remodel
01

Water and wood come first

Rot in the fascia, the siding and the door frame gets fixed before anything else. Paint over rot peels. A new door in a wet frame leaks. This step is the boring one and it is the one that protects everything after it.

02

Then the things with permits

The door needs a product approval and a permit. If the walkway touches the public sidewalk, so does that. Permits take time. They get filed early so the crew is never waiting on paper.

03

Paint goes on after the door, not before

A new door and new trim change the lines a painter cuts to. Paint first and you paint again around the new door. Paint last, and the whole front gets one clean coat.

04

The ground last

Walkway, landing, mulch and lights go in after the ladders are gone. Ladders and scaffolding wreck new pavers and plants. It sounds obvious. It gets done backwards every week.

The number of trades decides the price. The rot decides the surprises.

Two fronts can look the same and price far apart. Here is what actually moves the number on a front of house remodel.

01

How many of the five jobs are in

Door, siding, soffit and fascia, paint, walkway. Each one you add is its own material and its own days. The scope prices them as separate lines under one number. You can see what each one costs and drop one if you want.

02

How much wood is bad

The probing on the walkthrough finds it. A front with one soft fascia board is a repair. A front with rot at every window is a project. This is the line that moves most, and it is only known after the walkthrough.

03

The door you choose

A single fiberglass door with a factory finish is the base case. Sidelights, a transom, impact glass and wood all add. The door is often the single biggest line on the front.

04

Paint on one wall or the whole house

Painting only the front can look like painting only the front. Some houses can take it, most cannot. The scope prices both so you decide with the numbers, not with a guess.

What gets settled before any trade starts.

One scope with five trades in it only works if the order and the boundaries are written first. These are the things that get settled before the first ladder.

Hands holding a home inspection checklist on a clipboard, front of house remodel
01

The whole front probed and photographed

Fascia, siding bottoms, window trim, door frame and threshold. Soft spots get marked and photographed. You get the photos with the scope. Nothing on the front is a surprise later.

02

The order written into the scope

Rot, door, paint, ground. With dates. Each trade knows what has to be done before it arrives. That is what keeps the painter from painting a fascia that is about to come off.

03

Permits filed early

The door permit is filed the week the scope is signed. So is the right of way permit for the walkway, if it is needed. The door is ordered the same week. The crew starts on the rot while the paper moves.

04

Colors and the door picked once

The door, the trim color and the body color get chosen before anything is ordered. Changing the door after the trim is painted is a change order and a second coat.

05

Plants and the walkway protected

What stays gets covered. What goes gets removed first, not trampled. The new walkway is scheduled after the ladders, so it is never a work surface.

What is included, and where it ends.

A written scope is only worth something if it says where it stops. These are the lines we put in writing before anything is ordered.

Included in the scope
·Every board on the front probed and the bad ones listed
·Rot cut out, flashing set, new wood primed on all sides
·The front door unit, its approval number, permit and inspection
·Soffit and fascia on the front, vented where the attic needs it
·Wash, scrape, prime and paint the parts the scope names
·Walkway and landing repaired or rebuilt as named
·Plants, windows and the drive protected the whole time
·One final walkthrough for the whole front
Named separately, never assumed
·Roof work, including drip edge and shingles. The roofer, named when needed.
·Windows. Their own permit and their own scope.
·Landscaping beyond protecting what is there and resetting mulch.
·Electrical for new lights, doorbell or camera, by the licensed trade.
·The other three sides of the house, unless the scope names them.

How long the front is a job site.

Weeks, not days, and most of it is waiting. The door takes the maker's lead time. Paint waits for dry days. The trades run in order, so nobody is on top of anyone else. The house is always closed and dry at night. Your scope has the dates.

01
Walkthrough, front probed and photographed
02
Door ordered, permits filed
03
Rot cut out, flashing, new wood
04
Door set and inspected
05
Soffit and fascia finished
06
Wash, prime, paint in the dry window
07
Walkway and landing
08
Final walkthrough together

When we tell you not to do it

A front remodel is the job the whole street sees. That makes it easy to sell to someone who should fix something else first. Here is where we say no, and why.

The roof drips on the fascia

If the roof edge has no drip edge or the shingles are done, the front rots again under new paint. The roofer goes first. We say so, and we schedule after them.

The budget covers the door, not the wood

A beautiful door in a rotten front is a beautiful door in a rotten front. If the number only covers the door, do the rot now and the door next year. The order still holds.

You are selling in 60 days

A full front remodel does not return its cost in 60 days. A wash, a painted door, new numbers and a clean walkway often do. We would rather point you at the small list.

The plan is to paint first and see

Paint first means paint twice. If the door or the fascia is going to change, the paint waits. We will not put paint on a board that is coming off next month.

An older wooden house with peeling paint and a boarded window, where rot gets found before paint goes on

Lifetime warranty on our workmanship.

If the work we did fails, we come back and fix it. That holds for as long as you own the home. On a front remodel it covers what we built and set. The wood, the flashing, the door install, the prep under the paint, and the walkway base.

What the warranty covers
·New wood staying sound, with flashing behind it.
·The door staying square and sealing at the weather strip.
·Paint we applied on surfaces we prepped and primed staying bonded.
·The walkway sections we set staying level.
What it does not cover, said here and not in a footnote
·The products themselves. Door, boards, paint and pavers carry their makers' warranties, and we hand you that paper.
·Rot in wood we did not replace, which was already old.
·Damage from a roof leak, a gutter overflow or a sprinkler after the job.
·Fading and chalking from the Florida sun over the years.
·Plants and mulch after the final walkthrough.

A warranty is only worth what its exclusions say. Ours are above, in the same size type as the promise. Ask whoever you are talking to how long theirs runs, and get the number in writing.

Questions we actually get asked

What is included in a front of house remodel?

The five jobs the front usually needs. Rot repair on fascia, siding and trim. A new front door with its permit. Soffit and fascia, paint, and the walkway and landing. Each is a line in one scope. You can drop one. The order stays.

Why does the order matter so much?

Because each job wrecks the one that came before it if it is done backwards. Paint before the door means painting twice. Walkway before the ladders means broken pavers. Door before the rot means a new door in a wet frame. Wood, door, paint, ground.

Can you do the whole house or just the front?

Either. The front is the most common ask because it is what the street sees. Painting only the front works on some houses and looks odd on others. The scope prices both so you decide with numbers.

Do I need permits for a front remodel?

For the door, yes, in most Tampa Bay cities, along with its Florida Product Approval number. For the walkway, only if it touches the public sidewalk. For paint and siding repair, usually not. The scope names each one and who applies.

How long does it take?

Weeks. The door lead time and the dry days for paint set the calendar more than the labor does. Trades run one after another, in order. The scope has the dates and the house is closed and dry every night.

Can I do it in stages?

Yes. Rot and door this year, paint next year, walkway after. Each stage is its own scope. The one rule that does not bend is paint last. Paint on a board that is coming off is money gone.

The other exterior services

A one story stucco house with a green lawn, exterior remodel cost What an exterior remodel costs in Tampa Bay The 3 questions that move any front of house job between ranges. A white house wall with a dark front door, front door replacement Front door and entry door replacement A wind rated door with a number, a permit and an inspection. Close up of white lap siding on a house wall, siding repair Siding repair and replacement The board is easy. The flashing behind it is the job. Vented soffit panels under a roof edge with rain falling, soffit and fascia repair Soffit and fascia repair The rot is behind the gutter. The soffit is how the attic breathes.

All five exterior services

Where we work

Hillsborough, Pinellas, Pasco, Manatee and Sarasota counties. If your town is not on this list, call and ask: the answer is often yes.

Tampa Brandon Riverview Valrico Seffner Ruskin Apollo Beach Plant City Temple Terrace Lutz St. Petersburg Clearwater Largo Seminole Palm Harbor Safety Harbor Oldsmar St. Pete Beach Wesley Chapel New Port Richey

A walkthrough, then a written scope with one closed price.

Never hourly, never a verbal figure, and our workmanship carries a lifetime warranty. Hillsborough, Pinellas, Pasco, Manatee and Sarasota counties.

See a sample scope document
{{ sentMsg }}